Whirlwind Bike Earned Value Question

Whirlwind Bike Earned Value Question     
Planned cost (BCWS) week 6 194,000Planned Duration 12periods
Work PackageDurBAC%completeEVActual Cost
Start-up and mobilisation1           5,000100%        5,000                 5,000
Design frame2         60,00095%     57,000              57,000
Design wheels1         10,000100%     10,000              12,000
Design the ancillaries1         10,000100%     10,000              15,000
Build the frame4         60,0000%               –   
Build the wheels2         20,00070%     14,000              14,000
Build the ancillaries1         20,00090%     18,000              17,000
Integrate the bike2         40,0000%               –   
Test the bike2         20,0000%               –   
Launch the bike1           5,0000%               –   
Project Management 12         48,00050%     24,000              22,000
Total       298,000    138,000            142,000
      
CPI = EV / AC0.97    
SPI = EV / PC                0.71    
SV= EV – PC–          56,000    
CV = EV – AC–            4,000    
      
Actual completion = planned duration / SPI              16.87    
      
EAC = BAC/ CPI         306,638    
Square for website

Paul Naybour

 LinkedIn Profile
Paul Naybour is a seasoned project management consultant with over 15 years of experience in the industry. As the co-founder and managing director of Parallel, Paul has been instrumental in shaping the company's vision and delivering exceptional project management training and consultancy services. With a robust background in power generation and extensive senior-level experience, Paul specializes in the development and implementation of change programs, risk management, earned value management, and bespoke project management training.

4 thoughts on “Whirlwind Bike Earned Value Question”

  1. Adelle Well spotted I think its a rounding error on CPI. CPI is 0.971830985915493 so EAC is 306.6376811594203….excel……

  2. Hi – I’m a bit stuck and wonder if anyone can help please.

    If the BAC is 298,000 and the CPI is 0.97, shouldn’t that give a EAC of 307,261? Not 306,638

  3. Hi Paul,

    Fully understand how you arrived at your cals but the question then asks to draw the cost curves for EV and AC, How do you do this?

    Many thanks

  4. @epicday all you can do is plot the three points you have calculated and join with straght lines. So you have zero for all three at the start, AP and EV at week 6 and then the EAC and forcast actual completion.

Leave a Comment

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Upcoming Courses

Discover more about professional project management certification
and how it enhances the career prospects of individuals and the project delivery capabilities of organisations.

Scroll to Top